Montenegro's Upgraded TPP Pljevlja Capacity Raised to 223 MW

The installed capacity of Montenegrin thermal power plant (TPP) Pljevlja has increasedto 223 MW from 190 MW thanks to two upgrades in the past three years, state-controlled power utility Elektroprivreda Crne Gore (EPCG) said in the June edition of its corporate newsletter.

During this year’s 30-day annual maintenance the capacity of TPP Pljevlja was upped by a 5 MW while keeping coal consumption unchanged, EPCG said.

TPP Pljevlja generated 410,000 MWh of electricity in the first quarter of 2015, 5.5% ahead of plan. The power station delivered 1,317 GWh of electricity to the Montenegrin grid in 2014.

EPCG, which plans to raise output to 3,159 GWh this year from 3,036 GWh in 2014, operates around 870 MW of installed generation capacity. The company's net profit rose 38% to 34.7 million euro ($39 million) in 2014.

Source: SeeNews
EVENTS 1st Greek-Turkish Energy Forum Decarbonization Policies in South East Europe – between climate change and war

ADVISORY SERVICES Green Bonds

PUBLICATIONS The Greek Energy Sector 2023 South East Europe Energy Outlook 2021/2022 Long-Term Gas Contracting Terms, definitions, pricing - Therory and practice More

COOPERATING ORGANISATIONS IEA Energy Institute Energy Community Eurelectric Eurogas Energy Management Institute BBSPA AERS ROEC BPIE